Revised Closure Dates - the 3rd block of Main Street and the 3rd block of Chestnut Street will be closed starting September 27 for 7-14 days.
Construction Continues
Starting the week of September 27, the contractor will be working on sidewalks in the 3rd block of Main Street and on Locust Street from Hwy 283 to Poplar Street in front of the school. Please be cautious and do not walk on the new cement.
Around September 30, the 3rd block of Main Street and the 3rd block of Chestnut will be closed to through traffic for 7-10 days. Please use alternate routes.
The Streetscape project has begun! This project includes adding sidewalks, lighting, and trees to the third block of South Main Street and Locust Street from Oak to Poplar.
Starting Monday, September 6, the north side of Locust Street from Main to Chestnut will be closed. This area will remain closed possibly through October.
Please use caution while driving through the numerous construction areas currently in the City.